Short-Term Firm Point-To-Point Transmission Service Over Hydro Quebec DC Transmission Facilities
- The transmission service charge is as follows:
- Annual HQ-DC LTF Rate: $10,912.70 / MW-Year
- Monthly HQ-DC STF Rate: $909.40 / MW-Month
- Weekly HQ-DC STF Rate: $209.90 / MW-Week
- Daily HQ-DC STF Rate: $42.00 / MW-Day
- The daily rate is capped at the weekly rate.
Other charges are as set forth in ISO-NE FERC Electric Tariff No. 3, Schedule 21-NU.
Rates are based on estimated data and will be trued-up once actual costs are known.
|
 |