Contact Us NU Transmission Media Information

   Project Information for Customers
Customers Home Leadership Benefits Project Locations & Information Stay Informed Your Safety & Health Environmental Stewardship Questions & Answers  
NU Transmission >> Project Information for Customers Home >> Projects >> Manchester to Meekville Junction >> Project Description

New England East-West Solution (NEEWS)

Manchester to Meekville Junction
Project Description
Archived Documents
Contact Information

Middletown-Norwalk

LI Replacement Cable

Glenbrook Cables

Sherwood Substation

Agawam-West Springfield

Bethel-Norwalk

Project logoProject Description

Manchester to Meekville Junction Project
Click Map to Enlarge

Project Summary
What will be Constructed
Weekly Construction Update
Typical Construction Activities
Typical Work Hours
Work Activities – Hockanum River Trail System
Connecticut Siting Council – Project Approval
Development & Management (D&M) Plan
EMF Monitoring Plan & Maps

Project Summary

The Manchester to Meekville Junction Project in Manchester, Connecticut, consists of constructing a new 345-kilovolt (kV) transmission line on steel monopoles from the Manchester Substation to the Meekville Junction, reconfiguring the 345-kV line currently existing on double-circuit lattice towers, making changes to an existing line at each end of the project route, and modifying the Manchester Substation. All line work will take place on an existing CL&P right-of-way between existing lines.

Manchester to Meekville Junction Project Facts

Length: Approximately 2.7 miles,
constructed on existing right-of-way
Line voltage: 345 kilovolts
Town along right-of-way: Manchester, Connecticut
Siting approval: Connecticut Siting Council Decision & Order dated July 20, 2010
Project timetable:
  • Final engineering and environmental assessments
         began summer 2010
  • Construction scheduled to begin in fall 2011
  • Anticipated in-service date is estimated to be 2013
  • Typical view of what will be constructed in the area of the Hockanum River hiking trails and throughout the majority of the project route.





    Before Construction
    Before Construction




    After Construction
    After Construction

    Weekly Schedule

    Week of January 29, 2012

    Manchester - Construction Activity

    CLEARING - Crews will be clearing the right-of-way north of Tolland Turnpike and on the Hockanum River Area hiking trails on the south side of Middle Turnpike West. INSTALLATION OF ACCESS ROADS & CONSTRUCTION MATS - Crews will be installing access roads and construction mats on the right-of-way on the south side of Olcott Street and north of Tolland Turnpike. INSTALLATION OF FOUNDATIONS – Crews will be installing foundations on the right-of-way north and south of Olcott Street; on the Hockanum River Area hiking trails on the south side of Middle Turnpike West; and between the north side of Middle Turnpike West and the I-84 On Ramp. RELOCATION OF DISTRIBUTION POLES – Crews will relocate distribution poles and lines between Middle Turnpike West and the I-84 On Ramp.


    Back to Top

    Please note that these construction updates are subject to change without notice and that there may be occasions where unusual circumstances will require construction activities beyond normal work hours. When this occurs, every effort will be made to update this site with that information.

    Typical Overhead Construction Activities Construction

    Work typically, but not always, occurs in this sequence:

    • Creating work and storage areas
    • Right-of-way clearing
    • Work area preparation
    • Foundation installation
    • Existing structure removal
    • Structure installation
    • Wire stringing
    • Restoration
    Right-of-Way Clearing and Access Road Construction
    Right-of-Way Clearing and Access Road Construction
    Drilling of Foundations
    Drilling of Foundations
    Installation of Structures
    Installation of Structures
    Wire Stringing
    Wire Stringing
    Right-of-Way Restoration
    Right-of-Way Restoration

    Back to Top

    Typical Work Hours Work

    As directed by the Connecticut Siting Council (CSC), construction work hours are permitted 10 hours per day, between the hours of 7 a.m. and 9 p.m., Monday through Saturday.

    Work Activities Around the Hockanum River Trail System

    During construction, CL&P will work closely with the Hockanum River Linear Park Committee to minimize impacts to the trail system.

    During active construction in or around the park area, some trails will need to be temporarily closed to ensure public safety. Trail closings will be posted. Temporary signage will be installed to alert hikers of closed trails and trails will be periodically monitored during construction at trail crossings. Affected trails will be restored at the completion of construction. CL&P regrets any inconvenience this may cause.

    If you have any questions about the project's effect on the Hockanum River Trail System, please call our Project Hotline at 1-866-996-3397.

    Communications & Public Outreach

    Beginning with the Municipal Consultation and community outreach efforts related to the Manchester to Meekville Junction Project, CL&P has made a concerted effort to engage town officials, residents, businesses and other stakeholders to inform, answer questions and listen to concerns about the project.

    As work proceeds into and throughout construction, we will continue these outreach efforts.

    Back to Top

    Connecticut Siting Council – Project Approval

    On July 20, 2010, the Connecticut Siting Council (CSC) voted to approve the Manchester to Meekville Junction Project by granting the Certificate of Environmental Compatibility and Public Need. The vote followed a process that included a public comment session, field review and evidentiary hearings on CL&P's application. The project is designed to comply with mandatory federal and regional reliability standards.

    Read the CSC Decision and Order documents.

    Development and Management (D&M) Plan

    As part of the Connecticut siting process, CL&P prepared a construction plan for the Manchester to Meekville Junction Project, called a Development and Management (D&M) Plan, written in accordance with the CSC regulations and the Decision and Order. CL&P filed this plan with the CSC on December 10, 2010, and the plan was approved by the CSC, with conditions, on January 20, 2011.

    The D&M Plan provides the construction details for the project, including transmission line additions, modifications and relocations, as well as additions to the Manchester Substation.

    Prior to submitting the D&M Plan to the CSC, CL&P presented a draft version of the plan for public review and comment on September 7, 2010. CL&P revised the draft D&M Plan to address applicable comments received. As the project progresses, CL&P will continue to work with residents to address their questions or concerns about the project.

    Below is the D&M Plan filed with the CSC. The plan is subject to change.

    D&M Plan for Manchester to Meekville Junction Project:

    Back to Top

    Print page without header or side navigationPrinter Friendly Page

    Project Information for Customers Home | Energy Needs | Benefits | Projects
    Your Voice Matters | Stay Informed | Environmental Stewardship | Q&As
    NU Transmission Home | Media Information | Contact Us | Privacy Statement