Middletown-Norwalk
Project Description
Interactive Map
At-A-Glance
Frequently Asked Questions
Detailed Design (D&M) Plans
Resources and Links
Archived Documents
News and Updates
Contact Information
LI Replacement Cable
Glenbrook Cables
Waterford Substation
Bethel-Norwalk
Northeast Connecticut Reliability Project
New England East-West Solution (NEEWS)
Greater Springfield Reliability Project (GSRP)
Interstate Reliability Project (IRP)
Central Connecticut Reliability Project (CCRP)
|
 |
 |
 |
Norwalk
The route in Norwalk consists of new 345-kV underground lines and upgrades to an existing substation.
See the Route
What's Being Built
Construction Update
The Route Through Norwalk
(394KB)
What's Being Built in Norwalk
Underground Lines
In Norwalk, two new 345-kV transmission lines will be installed underground in a single duct bank. The route, from northeast to southwest, follows:
- Westport Avenue (US Route 1) - from Westport town line to North Avenue
- North Avenue (US Route 1) - from Westport Avenue to Father Conlon Place
- Main Street (CT Route 123) – from Father Conlon Place to south of Ohio Ave
- Off of Main Street passing under the Danbury Branch of the Metro North Railroad and emerging on Grand Street
- Grand Street – From Tindale Ave to New Canaan Ave (CT 123)
- New Canaan Ave (CT 123) from Grand Street to Norwalk Substation (located near the south bound side of Exit 2 off of Route 7)
Norwalk Substation
Two additional underground line circuits (From Singer Substation) and new 345-kV to 115-kV auto-transformers will complete the Middletown-Norwalk Project into southwest Connecticut. The existing 345-kV portion of the Norwalk Substation is an indoor gas-insulated substation providing a tie line into the existing 345-kV outdoor Norwalk Substation. The required gas-insulated equipment for this project will be constructed within the existing building and will add a second tie to the southwest Connecticut 115-kV transmission system.
Norwalk Construction Update
|
This Week: | May 12-17 | Duct bank trenching will occur adjacent to Westport Avenue between Hills Lane and Strawberry Hill Road, on North Avenue near Father Conlon Place, on Main Street between North and Union Avenues and adjacent to Main Street between Plymouth and Ohio Avenues. This work will occur approximately between 6 p.m. and 6 a.m | | Today: | May 17 | |