Middletown-Norwalk
Project Description
Interactive Map
At-A-Glance
Frequently Asked Questions
Detailed Design (D&M) Plans
Resources and Links
Archived Documents
News and Updates
Contact Information
LI Replacement Cable
Glenbrook Cables
Waterford Substation
Bethel-Norwalk
Northeast Connecticut Reliability Project
New England East-West Solution (NEEWS)
Greater Springfield Reliability Project (GSRP)
Interstate Reliability Project (IRP)
Central Connecticut Reliability Project (CCRP)
|
 |
 |
 |
Westport
The route in Westport consists of 5.5 miles of new 345-kV underground lines.
See the Route
What's Being Built
Construction Update
The Route Through Westport
(311KB)
What's Being Built in Westport
Underground Lines
In Westport, two new 345-kV transmission lines will be installed underground in a single duct bank. Traveling northeast to southwest, the 5.5 mile route follows:
- Post Road East (US Route 1) - from Fairfield town line to Imperial Avenue
- Imperial Avenue - from Post Road East (US Route 1) to Westport Women's Club
- Saugatuck River - Lines will be installed under the river
- Lincoln Street - from Riverside Avenue to Post Road West (US Route 1)
- Post Road West (US Route 1) - from Lincoln Street to Norwalk town line
Westport Construction Update
|
This Week: | May 5-10 | Work will occur on Post Road East at the Fairfield Town Line, between 9 a.m. and 3 p.m. and between 6 p.m. and 6 a.m. | | Today: | May 9 | | | Alerts: | Slow down for work zones! |
Bookmark this page and check back regularly for new information and important updates.

|
 |