Project Description: Sherwood Substation (Westport, CT)
 |
| Click Map to Enlarge |
CL&P is proposing to build a new 115-kilovolt (kV) - 13.8-kV bulk power substation in Westport, Connecticut. This substation will replace temporary equipment with a permanent solution, supply the growing load in the town of Westport, and strengthen the reliability of the local electrical supply in the area.
| Location: | 6 New Creek Road Westport, Connecticut |
| Operating voltage: | 115,000/13,800 volts (115/13.8-kV) |
| Regulatory review by: |
The Connecticut Siting Council and the Connecticut Department of Environmental Protection
|
| Timetable: |
- Municipal Consultation filing - September 2009
- Connecticut Siting Council application filing - December 2009
|

|
 |