 |
New England East-West Solution (NEEWS)
Manchester to Meekville Junction
Middletown-Norwalk
LI Replacement Cable
Glenbrook Cables
Waterford Substation
Project Description
Sherwood Substation
Agawam-West Springfield
Bethel-Norwalk
|
 |
 |
 |
Project Description
 |
| Click Map to Enlarge |
CL&P has energized a new 115-kilovolt (kV)/27-kV bulk power substation in Waterford, Connecticut. This substation will supply the growing load in the town of Waterford and will increase the reliability of the local electrical supply in the area. Please note that some construction will continue in 2010.
| Location: | 325 Waterford Parkway North, Waterford, Connecticut |
| Operating voltage: | 115,000/27,000 volts (115/27-kV) |
| Regulatory review by: |
The Connecticut Siting Council |
| Timetable: |
- Connecticut Siting Council application filed - June 2008
- Connecticut Siting Council public hearing - September 23, 2008
- Connecticut Siting Council approved the project - November 2008
- Development and Management plan approved by Connecticut Siting Council - February 2009
- Construction started in March 2009
- Substation energized - April 2010
|

|
 |